Happy New Year 2021!

24.12.2020

Dear clients and partners!
We congratulate you on the upcoming holidays and the New Year!

News Photo
The 2nd stage of transportation of the autoclave from the port of De-Kastri to Amursk has been successfully completed

23.12.2020

The transportation of the autoclave from Antwerp to Amursk for the second autoclave line of the Amursk MMC of Polymetal consisted of two stages.

News Photo
The delivery of ODC equipment from St. Petersburg to the site of JSC Taneco in Nizhnekamsk has been successfully completed

02.11.2020

Barrus Projects has successfully completed the ODC transportation for Alexander Global Logistics GmbH with further delivery to the site of JSC Taneco in Nizhnekamsk, part of PJSC TATNEFT.

News Photo
A unique project for the transportation of the largest in the world gold mining industry autoclave from Belgian Antwerp to Russia has been successfully completed.

23.10.2020

The equipment is intended for the second autoclave line of the Amursk Hydrometallurgical Plant (Amursk city) by JSC Polymetal. The general contractor of the transportation process was Key Point Logistics, which appointed Barrus Projects to carry out the contract work.

News Photo
Transportation of VESTAS nacelles to the Kalmykia and Kazachya wind farms has been successfully completed

16.10.2020

The transportation of 60 VESTAS nacelles was successfully carried out from the Liebherr-Nizhny Novgorod manufacturing plant. 48 nacelles were delivered to the construction site of the Salynskaya and Tselinskaya wind farms in Elista and the other 12 were delivered to the Kazachya wind farm in Rostov-on-Don.

News Photo
Barrus Projects at the “Retail in Russia” conference organised by Vedomosti, the leading business newspaper in Russia

17.09.2020

Barrus Projects took part in the XVII annual conference “Retail in Russia” which took place on 4 September in Moscow.

News Photo
The first phase of transportation of a key oversized cargo, a synthesis unit to SIBUR Tobolsk has been successfully completed

07.09.2020

As part of the project for construction of the very first maleic anhydride (MAN) production facility with a capacity of 45 thousand tons per year at the site of SIBUR Tobolsk, Barrus Projects team successfully completed a set of works on the transportation of heavy and oversized equipment from Germany to Russia, Tobolsk.