DELIVERY OF ROTORS HAS SUCCESSFULLY COMPLETED TO THE SOUTH URAL HYDROELECTRIC POWER STATION

The new rotor was delivered and installed after the dismantlement of the old rotor which was also delivered by our company and transported back by rail to the factory in Gorelovo.

Characteristics of the main OOG (rotor of gas turbine SGT5-4000F):

  • 11.5 õ 3.3 õ 3.3 m / 107.1 t

The project lasted for 5 months and included such works as preparation of transportation documents, the transportation of rotors via route “SGTT” plant – South Ural Hydrowelectric Power Station-2 and back, including obtainment of permits for oversized/heavy cargo and loading/unloading operations, development of necessary railway drawings.

BARRUS PROJECTS has also developed an individual cover for the rotor’s transportation by rail. The customer highly appreciated the quality of our work and once again trusted BARRUS PROJECTS with transportation of the rotor on a similar route.

Our company expresses gratitude for the trust and is honored to be a reliable partner of “Siemens Gas Turbine Technologies” for more than 10 years.