03.03.2022

Back to news

The transportation of a column for the complex for transshipment and fractionation of stable gas condensate and its products in the port of Ust-Luga has been successfully completed

Barrus Projects together with ANRI have successfully completed the transportation of a column for the complex for transshipment and fractionation of stable gas condensate and its products in the port of Ust-Luga via the route Dimitrovgrad - Tolyatti.

The main ODCs delivered from Dimitrovgrad were:

Column K-701 – 49.48 x 5.32 x 5.175 m / 122t;

During transportation modular axis and turntables, ownership of Barrus Projects were used, which made it possible to carry out delivery without delay, taking into account all the requirements of the client.

Our company is grateful for the trust and is glad to be a reliable partner of ANRI!