01.06.2023
DELIVERY OF OVERSIZE EQUIPMENT TO THE NUCLEAR POWER PLANT UNDER CONSTRUCTION
By order of “Rusatom Cargo” LLC, Barrus Projects delivered oversized cargo to the Ruppur NPP (nuclear power plant) in the Republic of Bangladesh. The construction site of the plant is located on the eastern bank of the Padma River, 160 km from the city of Dhaka, where a transport lock, vessels of the passive core flooding system and rotors were delivered.
The main OHC
The equipment, with a total weight of over 4000 tons, was delivered from the port of St. Petersburg, where our specialists organized its acceptance, storage, loading onto a vessel and shipped the cargo to the port of Mongla. After unloading the cargo in Bangladesh, transit and transshipment, the oversized equipment was transported by barge to the berth of the Ruppur NPP site with further trucking
The main OHC
- Equipment airlock, 1 pc., 12.73 x 9.86 x 9.96 m/ 275.17 tons
- Passive core flooding system vessel, 5 pcs., 10.69 x 4.89 x 4.74 m/ 81.34 tons
- Rotor, 1 pc., 10.97 õ 4.34 õ 4.44 m/ 99.46 tons
- Rotor, 1 pc., 10.3 õ 4.34 õ 4.44 m/ 99.11 tons
- Rotor, 1 pc., 10.3 õ 4.34 õ 4.44 m/ 98.22 tons
- Rotor, 1 pc., 10.3 õ 4.34 õ 4.44 m/ 99.32 tons
The equipment, with a total weight of over 4000 tons, was delivered from the port of St. Petersburg, where our specialists organized its acceptance, storage, loading onto a vessel and shipped the cargo to the port of Mongla. After unloading the cargo in Bangladesh, transit and transshipment, the oversized equipment was transported by barge to the berth of the Ruppur NPP site with further trucking