High-quality Fuel Plant in Uzbekistan (Uzbekistan GTL)

back

Equipment:

  • Nitrogen scrubbers, Air scrubbers, Absorbers, High pressure column

Route:

  • Saint Petersburg, Volgograd, Russia - port of Kuryk, Kazakhstan – construction site

Volume of cargo:

  • 1810 MT

Main oversize and heavy cargo:

  • Top column, 2 pcs. – 41,0 X 7,3 x 7,1 m; 225 t.
  • Lower column, 2 pcs. - 25,0 x 6,8 x 7,1 m; 120 t.
  • Adsorber, 4 pcs. - 27,0 x 6,0 x 6,4 m; 160 t.
  • Nitrogen scrubber, 2 pcs. - 20,0 x 6,0 x 6,2 m; 90 t.
  • Air scrubber, 2 pcs. - 28,0 x 6,9 x 6,7 m; 150 t.

Scope of work:

  • Loading of large-size heavy equipment on barges in two ways: RO RO and Crane method.
  • Development and coordination of the project of placement, ballasting and fastening of cargo on the barge.
  • Towing of barges from Saint –Petersburg via Volgograd to Kuryk.
  • Development of transport configurations of road trains for the Kuryk (Kazakhstan) - Karshi (Uzbekistan) route.
  • Reconstruction of infrastructure, construction of detours, strengthening of bridges and overpasses.